Two years ago, the state's plan to widen Highway 55 between Beacon Light Road and Brookside Lane had a construction year: 2029. Today it has none. In September 2026 the Idaho Transportation Department put the project on its unfunded list. Meanwhile, a 2019 agreement covering the same stretch of road still sets out when the lanes have to be built. That agreement doesn't follow a calendar. It follows a traffic count taken at the entrance to Dry Creek Ranch.
If you're weighing Dry Creek Ranch against other foothills communities, that difference shapes what your daily drive could look like over the next several years. The two-lane highway outside the neighborhood can be widened two ways. One depends on a state budget that just shrank. The other depends on how many cars turn into the community during the evening rush.
Three schedules in three years
The state project is ITD key number 23638. It would widen SH-55 from two lanes to four between Beacon Light Road, just north of Eagle, and Brookside Lane. Here is how its place in the state's seven-year plan has changed:
ITD program | Approved or published | Construction year | Listed cost |
|---|---|---|---|
September 19, 2024 | FY2029 | $11.443 million construction, plus engineering and $2.133 million for right-of-way | |
June 12, 2025, public comment | FY2032 | $12.054 million total | |
September 17, 2026 | None; Early Development, unfunded | $7.553 million construction estimate |
The approved FY2027 program describes the project as a widening "in order to mitigate congestion." It lists engineering and right-of-way money in the same unfunded column as construction.
The region's planning agency hasn't fully caught up. COMPASS, the Treasure Valley's metropolitan planning organization, still shows the widening in its FY2026–2032 project list for 2032 at $17.251 million. COMPASS's May 2026 draft of its next list also shows a $984,000 right-of-way line for 2027, funded by a "Private Developer." The draft doesn't say which developer. Because ITD's approved September program is the newer document, its listing is the one that controls.
Why the state's version stalled
The project didn't stall over anything specific to Dry Creek Ranch. It stalled over a statewide budget decision. According to the Idaho Statesman's reporting, republished by East Idaho News, the Legislature removed $275 million in transportation funding for the coming fiscal year: $165 million for state highways and $110 million for local highway districts. That money came from the Strategic Initiatives Fund, which ITD now expects to stay at zero through 2033. The same report says the fund made up about 18% of ITD's revenue in 2025 and was meant to speed up large congestion projects.
ITD's June 2026 board minutes describe the response. The department rebalanced its program around pavement, bridges, and its core duties, and moved more than $1 billion in projects into Early Development. In that same reporting, ITD highway division administrator Amy Schroeder said the department planned to "keep project development moving to the greatest extent possible" on unfunded projects and was pursuing grants, so designs would be ready once revenue returns.
So the state's version of the widening has moved from "scheduled" to "ready when money appears." The second track doesn't wait on that money.
The clause that doesn't need a budget
When ITD approved the traffic signal at SH-55 and Brookside Lane in 2019, it explained in a September 30, 2019 news release that the light was temporary and would be paid for by the developer, Boise Hunter Homes. ITD also described an agreement among the developer, Ada County, and the department that ties future highway work to growth, measured as evening rush-hour trips into the development:
- At 550 trips per hour, the developer must add a travel lane in each direction on SH-55 from Beacon Light Road to a few hundred feet north of Brookside Lane.
- At 1,300 trips per hour, the developer must remove the signal and build a different intersection that lets traffic flow freely at 55 mph.
The release said ITD collects this trip data every year. The count at the time was 100 trips per hour, and the most recent public figure is that 2019 baseline. ITD added that a similar agreement covers Avimor, farther north on the highway.
The release also quoted Amy Revis, then District Engineer for ITD's Southwest Idaho offices:
"ITD's long-range vision for this section of ID-55 requires the corridor to be free of signals north of Beacon Light. We often phase implementation of improvements to meet current and near-term traffic demand, allowing the development to generate revenues which can fund the ultimate mitigation improvements."
That quote explains how the corridor's funding was designed. The state lets the signal stand while traffic is light. Home sales are expected to pay for the bigger fix later, and growth itself sets the timing. By June 2022, BoiseDev reported that the Brookside light was operating as Dry Creek Ranch's main entrance.
For a buyer, this means the light you wait at on your first drive in was approved as a temporary fixture. It's tied to thresholds that move with the community's own build-out, which BoiseDev described as an 1,800-home plan.
A second light, approved as an exception
Brookside isn't the only intersection in this story. In February 2023, the Idaho Transportation Board approved resolution ITB23-09. It grants an access-spacing exception for a signal at SH-55 and Dry Creek Road, which sits closer to the Brookside light than state rules normally allow.
The board packet lays out the case. Dry Creek Ranch, Hidden Springs, and Cartwright Ranch together had 3,475 approved homes and about 6,000 residents. All of them shared one signalized intersection onto SH-55, and more development was expected in northeast Eagle and Avimor. A 2016 traffic study had recommended two signals, and a 2022 analysis showed signals were warranted at both intersections. The planned community also allows 10 acres and 85,000 square feet of commercial space. The HOAs for Dry Creek Ranch and Hidden Springs supported the signal. ITD reported some opposition from residents and from the City of Eagle, whose main concerns were sight distance and safe operation on a slight bend in the highway.
Under the existing development agreement, that intersection had been limited to right-in, right-out turns, so the board treated the request as an appeal. ITD recommended a "Green-T" design: southbound highway traffic keeps moving freely while left turns in and out get a signal. The developer agreed to pay the full cost of design and installation. BoiseDev covered the approval on February 27, 2023.
The Green-T fits with the 2019 framework. It keeps one direction of highway traffic flowing, in line with ITD's goal of a signal-free corridor, and it adds another way in and out for the three communities. Like Brookside, its cost falls to the developer and not to the state program that just lost its funding.
What the original traffic plan expected
The road question goes back to the community's approval. Ada County's adopted Dry Creek Ranch plan included a traffic study from roughly 2009–2010. It forecast that the Beacon Light-to-Brookside segment would need four lanes once the community reached 50% completion, which the study defined as 20,000 external daily trips. It also projected that Dry Creek Ranch would produce about 73% of peak-hour traffic on that segment at full build-out. The interim plan called for widening the Brookside intersection, adding a temporary signal, and having Dry Creek Ranch pay fully for those improvements without a financial burden on public agencies.
Those forecasts are more than 15 years old and rest on phase years that have passed, so they aren't a guide to current traffic. They do show that from the start, the plan expected this community to account for most of the demand on this segment and to pay for its first fixes. The 2019 trip thresholds turned that expectation into specific numbers.
Questions to bring to a Dry Creek Ranch purchase
The highway outside Dry Creek Ranch is still being planned, and its timing affects a purchase there. These questions can help you put it in perspective:
- Which track is moving? The state's widening is listed as unfunded in ITD's FY2027–2033 program. The developer obligation is triggered by evening-peak trip counts that ITD says it collects every year.
- Which entrances serve the street you're looking at? Brookside Lane is the main signalized entrance, and the Dry Creek Road Green-T was approved in 2023. Your route home depends on which one sits closer to the lot.
- What does the commercial plan add? Ada County expected commercial and village build-out between 2025 and 2032, according to BoiseDev's 2022 report. The 85,000 square feet of planned commercial space was one reason given for the second signal.
- Who else uses this segment? Avimor has its own growth-based agreement, and the 2023 board packet named northeast Eagle as another source of new traffic.
The development agreements and state programs mentioned here are public documents. This post is general information, not legal or financial advice, so confirm how any agreement affects a specific property with the appropriate professional.
Quick answers
Is Highway 55 being widened near Dry Creek Ranch? The state's project, key 23638, is in ITD's approved FY2027–2033 program as unfunded, with no construction year. A separate 2019 agreement requires the developer to add a lane in each direction when evening-peak trips into the development reach 550 per hour.
Is the Brookside Lane signal permanent? ITD approved it in 2019 as an interim signal. Under the agreement, it is to be replaced by a free-flowing intersection when trips reach 1,300 per hour.
Why did the state project lose its funding? The 2026 Legislature removed $275 million in transportation funding, and ITD moved dozens of growth-related projects into its unfunded Early Development category.
Does the COMPASS 2032 date still apply? COMPASS's FY2026–2032 list shows 2032, but ITD's newer approved program, adopted September 17, 2026, lists no construction year.
If you're comparing foothills communities and want to know how Brookside, Dry Creek Road, and the SH-55 plans would affect the drive from a specific street, Jay De Beer can go through the ITD and Ada County documents with you before you write an offer. Let's Connect.